Which Time Zone Does Your Contractual Deadline Expire In?


Maritime contracts run on deadlines. Hire is payable by a date. A notice of readiness starts a period. A demurrage claim must be notified and documented within set times. A cancellation right opens at a fixed point.
Each of those deadlines ends at a moment. When the parties, the bank, and the port are in different places, which clock fixes that moment is a question the contract often leaves open.
Two English decisions have now addressed it, and the principle running through both is usable. What is a contractual deadline time zone?
Songa: The Day Ends Where the Obligation is Performed
In Songa Product and Chemical Tankers IV AS v Gardsea Shipping Inc [2026] EWHC 1559 (Comm), decided on 23 June 2026 by Paul Stanley KC sitting as a Deputy High Court Judge, the Commercial Court heard a section 69 appeal from an LMAA award on the construction of a ship sale contract based on Saleform 2012.
The sellers agreed to sell the MT Songa Coral for USD 25 million. Clause 3, as amended, required the buyers to preposition the balance of the purchase price in an escrow account at Nordea Bank in Norway at least one banking day before expected delivery, where it remained at the buyers’ order. On delivery, but not later than three banking days after notice of readiness, that balance was to be released from the escrow account to the sellers’ account, also at Nordea in Norway.
Banking Days were defined as days on which banks were open in the country of the currency, in the place of closing, and in the United States, Canada, the United Kingdom, Switzerland, Turkey, the UAE, Greece, and Norway.
Notice of Readiness was given on Friday 2 September 2022. The weekend did not count. Monday 5 September did not count because it was Labor Day in the United States and Canada. The tribunal held, with no appeal on the point, that 8 September was a banking day despite a local holiday in the Canton of Geneva. So the three banking days expired at the end of 8 September.
No payment had reached the escrow account by midnight in Norway. At 00:09 Norway time on 9 September the sellers served a notice of cancellation. Midnight had not yet arrived in the UK, Canada, or the United States, and in Hawaii it was still the afternoon of 8 September.
The tribunal, which included Sir Jeremy Cooke, held for the buyers, that the deadline ran to midnight Hawaii-Aleutian time, the westernmost jurisdiction in the definition. The Commercial Court held that conclusion legally incorrect.
What The Judge Actually Decided
The reasoning is worth following because it is portable.
A banking days definition identifies which days count, not what a day is. The judge held that the definition “does not answer the question what is a day? but the different question which days are Banking Days, and in my view does nothing more than that.” It takes the calendar day as given and marks certain dates as countable.
The buyers’ reading produced something that is not a day. On their construction the period would run 37 or 38 hours, beginning at midnight in the UAE and ending at midnight in Hawaii, passing through three calendar dates, with a second overlapping day already running. The judge thought it unlikely “that it would occur to many people to think of such a period as a ‘day’ at all.”
So, you fall back on the ordinary rules. The time is midnight, following The Afovos. The place is found “by considering where the act in question has been or is to be performed.”
The judge was careful about the status of that principle. He declined to treat it as a rule of law requiring clear words to rebut, calling that “algorithmic approach to interpretation” rarely apt, and described it instead as “a natural and a reasonable and (usually) workable starting point, in touch with ordinary ways of thinking about time.”
He put the commercial sense of it plainly. If a business person says they will make sure you have the payment in Norway by Tuesday, “they will not normally be understood to mean ‘by some time on Wednesday morning, which is still Tuesday somewhere else’.”
The escrow agreement was not the reason. The escrow agreement separately referred to Norwegian banking days. The judge expressly declined to attach significance to it, saying he did not think “any significance attaches to the fact that the parties (after the conclusion of the MOA) expressly referred to ‘Norwegian banking days’ in the escrow agreement,” since that did no more than fix the criterion for counting days for one particular purpose. The decisive point was simply where the release obligation was performed, which was Norway, and which the judge noted is equally clear under the unmodified Saleform.
What about the appeal? The appeal was on a preliminary issue. The judge held that the buyers were in default if release had not occurred by midnight Norway time on 8 September. He noted expressly that “there may be various other issues” which were not before the arbitrators on the preliminary issue and were not before him. The decision resolves the deadline question, not every aspect of the cancellation.
The Maria: The Same Principle on a Time Bar
The question is not confined to sale contracts. In Euronav N.V. v Repsol Trading S.A. (The Maria) [2021] EWHC 2565 (Comm), Henshaw J considered a demurrage claim under a Shellvoy 6 charter.
The charter contained two separate requirements: notification to charterers that demurrage had been incurred within 30 days of completion of discharge, and a fully documented claim within 90 days. The dispute concerned the 30-day notification.
Discharge completed at Long Beach on 24 December 2019 local time. Owners notified on 24 January 2020. If 24 December was the date of completion, the last day for notice was 23 January and the claim was barred. If a different time zone applied, making it 25 December, the notice was in time.
Henshaw J held that where a clause runs a specified number of days from completion of discharge, the date is fixed by local time at the place where the event occurred, not by the time zone of either contracting party and not by GMT because English law governed. He described the starting point as being “that the date of an event should normally be determined using local time at the place where the event happened.”
The Songa judge relied on that passage directly, calling it a demonstration of the principle’s continuing vitality.
Where This Reaches in Operations
The two decisions cover a payment obligation and an event-triggered time bar. The reasoning applies more broadly.
Time Charter Hire: A party obliged to do something by a date has until midnight on that date, following The Afovos. On the Songa reasoning, the end of the due date is midnight where the payment obligation is performed. Where hire is payable into an account in a particular jurisdiction, the due date is likely to expire at midnight there, whatever the vessel’s position or the parties’ own locations.
Anti-Technicality Notices: These generally cannot be served until charterers have actually failed to pay by expiry of the due date. If the due date ends at midnight in the place of payment, a notice served before that is premature. ASBATIME clause 29 ties both the notice period and its reference point to one place, giving charterers two clear banking days as recognized at the agreed place of payment.
Demurrage Time Bars: The Maria is directly on point, and note that a charter may contain more than one deadline running from the same event.
Cancelling Dates and Option Periods: Songa itself touched on clause 5(c) of the Saleform, where buyers have three banking days to respond to a proposed new cancelling date. The judge noted the starting point is the date the buyers receive the notification and the end point the date they respond, with the contract’s notice provisions fixing the relevant locality.
Declaration and Notification Obligations: Newer clauses carry reporting duties, including the BIMCO USTR Clause and Chinese Special Port Fee Clause provisions on vessel nexus declarations and notification of changes. Those are framed around requests and reasonable practicability rather than fixed midnight deadlines, so Songa does not apply to them directly. They are worth reviewing in the same exercise because they are time-sensitive obligations spanning jurisdictions.
What the Court Will Look At
An express time zone governs. If the contract names one, that ends the analysis.
Otherwise, identify where the obligation is performed, or where the triggering event occurred. For a payment, that is normally where payment is to be made. For an event-triggered period, it is where the event happened.
A multi-jurisdiction definition identifies days, not hours. Naming eight countries in a banking days definition tells you which calendar dates count. It does not extend the day to the last midnight available among them.
Do not expect a separate agreement to settle it. In Songa the escrow agreement’s Norwegian banking days wording was held not to be significant.
What To Do About It
Specify the time zone for any deadline that matters. By midnight Norwegian time, or by 5:00 pm London time. The judge observed that where parties want a definitive answer, it is given “by specifying one time zone which is to be determinative for all purposes, not by specifying twelve.”
Identify where each obligation is performed and where each triggering event occurs. For payments, the agreed place of payment. For event-triggered deadlines such as completion of discharge, the local date at the place of the event. For notices and document submissions, read the service and receipt provisions rather than assuming the recipient’s location governs, because whether a clause requires sending or receipt within the period is a separate question the time zone analysis does not answer.
Check public holidays in every named jurisdiction. In Songa, a US and Canadian holiday removed a day from a Norwegian payment deadline. Eight countries in a definition means eight holiday calendars.
Do not plan to use the full period. The judge acknowledged that a dollar payment will likely involve an American bank and that the period “may indeed be squeezed a bit” if the deadline expires before US banks close, but held that parties “can be expected to make sure they will be in a position to do so, or to stipulate for additional time if that is foreseeably required.”
Work to the earliest plausible expiry. Where the governing time zone is genuinely unclear, use whichever reading gives you least time.
Take as much care serving early as serving late. A premature anti-technicality notice may be invalid. A termination served before a deadline has passed may itself be a breach. Songa turned on nine minutes, and the exposure runs both ways.
Where the insurance sits
FD&D: Freight, demurrage and defence cover responds to the costs of pursuing or defending claims of this type, including demurrage disputes and charter party arguments involving no physical loss. Whether a notice was validly served, or a claim presented in time, is the kind of question it exists for. Cover is subject to the club’s rules and to the merits of the claim.
What is Not Covered: A commercial loss from a missed deadline is not an insured peril. If a termination right is lost, a claim becomes time barred, or a vessel is withdrawn because funds arrived late, that is a contractual outcome. The drafting and the diary are the risk controls.
The Bottom Line
Where a contract sets a deadline and more than one time zone is in play, the English courts look to midnight at the place where the obligation is performed or where the triggering event occurred. A banking days definition spanning several countries identifies which calendar dates count toward an interval. It does not stretch the day to the last midnight available among them.
In Songa the gap between those readings was about twelve hours, and a notice served nine minutes after Norwegian midnight was either effective or premature depending on which applied. In The Maria the same principle decided whether a demurrage claim existed at all.
Both were available to be settled at the drafting stage by naming one applicable time zone. Where that is missing, the next best protection is knowing where each obligation is performed and working to the earliest deadline that produces.