Case Law: Force Majeure in Shipping Contracts

Writer: Richard Young
Richard Young
Nov 11
15 min read
Vessel at port

A charterer’s cargo is stuck behind a strike. A sanctions designation makes payment difficult. A waterway is blocked. In each case someone will reach for the force majeure clause, and what happens next depends almost entirely on what that clause says.


English law approaches this differently from most civil law systems, and the UK Supreme Court addressed the central question in 2024 in a case arising out of OFAC sanctions on a charterer’s parent company. This article sets out how force majeure works under English law, what that decision established, and what the BIMCO model clause does about it.


There Is No General Doctrine of Force Majeure in English Law

This is the starting point and it is frequently misunderstood by parties coming from other legal traditions.


BIMCO states the position plainly in its own explanatory notes. Under English law a party will be in breach of contract for not performing even if the reason is force majeure, because force majeure is not a legal concept recognized under English law as it is in most civil law jurisdictions, France being the example BIMCO gives, where force majeure is part of the Code Civil.


Force majeure under English law is therefore a creature of contract. If the contract contains no force majeure clause, there is no force majeure relief, and the party is left with the doctrine of frustration, which is far narrower.


Every force majeure question is accordingly a question of construction.


What a Force Majeure Clause Has to Establish

The Supreme Court in MUR Shipping set out the general position by reference to the leading textbooks. Chitty on Contracts describes the type of event likely to fall within such a clause as one that was beyond the reasonable control of the parties, and so would not include an event caused by the negligence, omission or default of one of the contracting parties; was causative of the non-performance; and could not have been overcome or avoided by the taking of reasonable steps.


Benjamin’s Sale of Goods puts the same point as a burden on the party invoking the clause. Treitel notes that the concept of something beyond a person’s control sets a comparatively high hurdle.


Three elements, then. The event must fall within the clause, it must cause the failure to perform, and it must not have been avoidable by reasonable steps.


Reasonable Endeavors Are Generally Required Even Without an Express Proviso

The Supreme Court held that a force majeure clause will generally be interpreted, or a term implied to the same effect, as applicable only if the party invoking it can show that the event was beyond its reasonable control and could not be avoided by the taking of reasonable steps.


The court was explicit that this is not an unusual feature but a very common one. On the clause before it, which contained an express proviso at 36.3(d) requiring that the event “cannot be overcome by reasonable endeavors from the Party affected,” the court said that even without that subclause the contract would have been interpreted as containing a reasonable endeavors proviso to like effect.


The court also held that no particular significance attached to the word “overcome.” The equivalent wording in the textbooks and authorities is “avoid,” carrying the same meaning in this context, as would synonyms such as negate, neutralize, nullify, defeat, prevent or remove.


The requirement goes back a long way. In Bulman & Dickson v Fenwick & Co [1894] 1 QB 179, Lord Esher MR said a strike would not itself exonerate charterers from doing the best they could to accept delivery, and would not entitle them to fold their arms and do nothing. In B & S Contracts and Design Ltd v Victor Green Publications Ltd [1984] ICR 419, Griffiths LJ said such clauses have to be construed on the basis that those relying on them will have taken all reasonable efforts to avoid the effect of the matters set out in the clause. In Channel Island Ferries Ltd v Sealink UK Ltd [1988] 1 Lloyd’s Rep 323, Parker LJ said a party must not only bring itself within the clause but must show it has taken all reasonable steps to avoid its operation or mitigate its results.


All of this is subject to the wording the parties actually agree. The court was equally clear that clear words can produce a different result.


MUR Shipping: What Reasonable Endeavors Does Not Require

RTI Ltd v MUR Shipping BV [2024] UKSC 18, decided 15 May 2024, is the leading modern authority.


The Facts: In June 2016 MUR Shipping, a Dutch owner, and RTI, a Jersey charterer, entered a contract of affreightment on an amended Gencon form for the carriage of about 280,000 tonnes per month of bauxite from Conakry in Guinea to Dneprobugsky in Ukraine over two years. Freight was payable in US dollars.


On 6 April 2018 OFAC applied sanctions to RTI’s parent, United Company Rusal plc. RTI itself was not listed, but a majority-owned subsidiary of a listed entity was subject to the same restrictions.


On 10 April MUR gave a force majeure notice under clause 36, saying payment in US dollars as required by the contract was prevented by the sanctions. RTI rejected the notice and offered to pay in euros, bearing any additional costs or exchange rate losses on conversion. MUR maintained its right to dollars, treated performance as suspended and refused to nominate vessels. RTI chartered in seven replacement vessels and claimed damages.


It became common ground that the sanctions did not prohibit dollar payment, but that timely payment would highly probably have been delayed, because any dollar transfer would have had to pass through a US intermediary bank which would initially have stopped it pending investigation, and that this could not practicably have been avoided by using a bank outside the United States.


The Issue: Whether a reasonable endeavors proviso can require the affected party, if it is to rely on the clause, to accept an offer of non-contractual performance from the other party.


The Course of the Litigation: The arbitrators held against MUR, dealing with the point in two paragraphs of a 156-paragraph award and without reference to case law. Jacobs J reversed. The Court of Appeal majority restored the award, Arnold LJ dissenting. The Supreme Court allowed MUR’s appeal.


The Holding: Absent clear wording, a reasonable endeavors proviso does not require the affected party to accept an offer of non-contractual performance.


The Four Reasons the Court Gave

Each is portable to other clauses and other facts.


Reasonable endeavors provisos are about causation. A party is excused where the failure to perform is caused by the force majeure event. It is not so caused if the affected party could reasonably have prevented the failure, because then the cause is the affected party’s inadequate response rather than the event. Contractual performance means performance of the contract according to its terms, and the object of the reasonable endeavors proviso is to maintain contractual performance, not to substitute a different performance.


Applied to the facts, the relevant question was whether reasonable endeavors by MUR would have enabled payment in US dollars without delay. Obtaining a specific license might have done so. Accepting euros did not, because the impediment to contractual performance remained untouched. As the court put it, it would be absurd to say that MUR caused the non-performance of the contract by failing to accept an offer of non-contractual performance.


Freedom of contract. The principle includes freedom not to contract, and freedom not to contract includes freedom not to accept the offer of a non-contractual performance of the contract.


Clear words are needed to give up valuable contractual rights. MUR had a contractual right to be paid in dollars and to refuse any other currency. The court treated it as a general principle of contractual interpretation that parties do not forego valuable rights without it being made clear that that was their intention, and clause 36.3(d) addressed neither the giving up of the right nor the circumstances in which it would be required.


Certainty in commercial contracts. The court worked through what RTI’s test would require. Inquiries into whether acceptance involved “no detriment” raise questions about what detriment means, whether minor costs count, whether an offer to bear them cures it, and when and over what period it is assessed. Inquiries into the “purpose underlying” an obligation assume a single identifiable purpose, which is often not so. All of this would be retrospective and unpredictable, in the context of a clause requiring immediate judgments. Parties need to know with reasonable confidence whether a force majeure clause can be relied on at the relevant time, not after a retrospective inquiry.


The court rejected the framing of this as certainty winning over reasonableness, saying it is not unmeritorious or unjust to insist on contractual performance, all the more so if being precluded from doing so would introduce uncertainty contrary to the expectations of reasonable business people.


What the Decision Does Not Say

Two qualifications in the judgment itself:


Parties can provide otherwise by clear wording. The court said it was not in dispute that by clear words the parties can provide for reasonable endeavors to include accepting an offer of non-contractual performance. The default is a default, not a prohibition.


What counts as contractual performance is itself flexible. The court observed that the position would have been different if RTI had been able to perform by paying in either US dollars or euros. Where an obligation can be performed in alternative ways, performing either is contractual performance.


Alternatives and Options Are Not the Same Thing

This distinction decides a lot and it is easy to collapse.


Where one obligation can be performed in alternative ways, blocking one route does not excuse performance by another. Lord Devlin’s formulation in the Vancouver Strikes case is that the consequence of damming one channel is simply that the flow of duty is diverted into the others and the freedom of choice thus restricted.


Where a party holds what Lord Devlin called a business option, the position is different. There is one obligation to be performed in one way unless the option holder chooses to substitute another by effective exercise of the option, and in exercising an option acquired solely for its own advantage the holder is not bound to consider the convenience or interest of the other party.


In Reardon Smith Line Ltd v Ministry of Agriculture, Fisheries and Food [1963] AC 691, charterers ordered to load a full cargo of wheat at Vancouver, with options to load up to one third barley and up to one third flour, were held entitled not to exercise those options when a strike prevented a full wheat cargo, and could rely on the strike exception.


The limit appears in Seadrill Ghana Operations Ltd v Tullow Ghana Ltd [2018] EWHC 1640 (Comm), where Teare J held that a party with an obligation to give drilling instructions capable of performance in a number of ways had to give instructions that could be performed, and was not entitled to act purely in its own commercial interests. The argument that this was a true option was rejected.


So the question in any case is whether what the contract creates is an obligation with alternative routes or a discretion held by one party. That distinction has to be carried into drafting, because inserting an alternative port or currency does not necessarily produce the result you want.


Force Majeure Is Not Frustration

The court drew the distinction clearly.


Frustration is the default position laid down by law. It applies in a narrow range of changed circumstances and has the drastic consequence that the contract is automatically terminated. Force majeure clauses can cover a far wider set of circumstances with a range of different and more flexible consequences, including temporary suspension for a period.


Counsel for MUR put it in submissions, "if force majeure clauses simply mirrored the common law of frustration, they would be pointless."


Reasoning across from frustration cases is therefore unreliable. The court rejected RTI’s argument from the Suez cases on that basis, and separately held that in The Eugenia [1964] 2 QB 226 the Court of Appeal had not required charterers to accept non-contractual performance at all. Lord Denning MR held there was no obligation to go through the Suez Canal, only to go by the route customary at the time of performance, and the customary route had become the Cape of Good Hope. What was offered was contractual performance.


The court also rejected an argument from mitigation based on Payzu Ltd v Saunders [1919] 2 KB 581, holding that mitigation concerns the remedy of damages once breach is established and has little to do with the prior question of whether there has been a breach of the primary obligations.


BIMCO addresses the same relationship from the drafting side. Its explanatory notes record that the immediate termination trigger in its clause deliberately mimics the English law doctrine of frustration, which gives access to the frustration case law, while allowing immediate termination rather than requiring the passage of time. The notes also observe that frustration is a residual remedy under English law and may not be available where the parties have provided for the event contractually, which is why a frustration-like remedy was codified in the clause.


Notice Provisions Can Defeat a Claim on Their Own

The clause in MUR Shipping required a force majeure notice within 48 hours, Saturdays, Sundays and holidays excepted, of the party becoming aware of the event, setting out details, stating that the party wishes to claim force majeure, and giving a reasonable estimated duration so far as reasonably possible.


Clause 36.5 then provided that a party failing to give notice in accordance with that provision shall not be permitted to claim force majeure in respect of the event. That is a complete answer regardless of the merits.


A deadline in elapsed hours is not the same as one in calendar days. Forty-eight hours runs for the same duration wherever the parties sit, so the time zone analysis that applies to a deadline expressed in days does not transfer directly. What does create uncertainty is the exclusion of Saturdays, Sundays and holidays, because that requires knowing whose calendar applies and which hours drop out. Specify the calendar, the method of calculation, and when notice is deemed received.


BIMCO takes a different approach. Its clause requires written notice “without delay” rather than within a fixed period, and the explanatory notes give the reason. It can be difficult to identify at what point in time the event occurred. The incentive to move quickly comes from elsewhere in the clause, which excuses the affected party from breach only from the time notice is given. The notes record that parties may substitute a specific number of days if they prefer.


The BIMCO Force Majeure Clause 2022

BIMCO publishes a model force majeure clause, and it is worth reading alongside MUR Shipping because it addresses most of the questions the case raises.


It carries an unusual health warning. BIMCO states at the top of the clause that it is a model clause which should not simply be included in a contract without first carefully reviewing it against the other clauses, and urges caution when including it in a period time charter party with a broad trading area. The explanation is that charterers under a time charter are entitled and obliged to provide orders for the ship’s employment, so a charterer who orders a ship into a force majeure situation will normally be able to resolve it by finding alternative employment. The clause may still be relevant for a dedicated trade or where cargo is already on board.


The threshold is high and includes foreseeability. The affected party must prove the existence of a force majeure event from the defined list, that it is beyond its reasonable control, that it could not reasonably have been foreseen at the time of conclusion of the contract, and that its effects could not reasonably have been avoided or overcome. BIMCO’s rationale for the foreseeability limb is that if something is foreseeable the parties should contract their way around it rather than relying on a force majeure clause.


The unavoidability test tracks the MUR Shipping position. The clause asks whether effects could “reasonably” have been avoided or overcome, which BIMCO notes follows the ICC Force Majeure Clause 2020, where the guidance explains that reasonableness sets a lower threshold than impossibility.


The event list is detailed and carves out your own negligence. It covers war and hostilities, piracy and seizure, blockade and trade restriction, acts of government, epidemic and pandemic, acts of God and extreme natural events, explosion, fire, obstruction of waterways, cyber security incident and breakdown of transport or power supply, radiation and contamination, and general labor disturbance.


Several categories carry a carve-out for the affected party’s own negligence, and the labor disturbance limb does not apply where the disturbance is limited to the affected party’s own employees. BIMCO explains that a general negligence carve-out was not applied to events like war or earthquake because it would impose a negative burden of proof.


Sanctions are deliberately not covered. BIMCO states that “generally imposed trading restriction” is not intended to cover sanctions but means restrictions placed on imports or exports to protect domestic markets. It directs parties to its separate sanctions clauses for voyage charters, time charters and container vessel time charters. Anyone relying on the BIMCO force majeure clause to handle a MUR Shipping situation would find it does not reach.


Payment obligations continue unless directly affected. The clause provides that nothing in it affects either party’s payment obligations unless those obligations are directly affected by the force majeure, and BIMCO confirms this covers both accrued and ongoing obligations.


There is a cooperation duty. The parties are to cooperate to minimize the effects and discuss in good faith alternative ways in which the contract can be performed. BIMCO describes this as the spirit of the clause, with termination as a last resort.


Two routes to termination. Immediate termination where performance is rendered impossible, illegal or radically different from what was intended, which is the frustration-like test. Or termination after a stated number of days where the force majeure substantially affects performance of the contract as a whole. BIMCO emphasizes in bold that the second route does not apply at all unless the parties insert a number in the blank, and advises shorter periods for short-term contracts and longer for long-term ones.


Supplementary wording for charter parties. BIMCO proposes two further subclauses. One confirms that force majeure does not affect time on hire or laytime and demurrage, which it says mirrors the English law position and is useful because the position is less clear elsewhere, and limits termination under a contract of affreightment to the affected shipment rather than the whole contract. The other addresses cargo already loaded, barring termination while cargo is on board and providing a structured set of options after twenty-one days, with a fallback right to discharge at the nearest safe port if the other party does not respond within seven days.


And a note on bills of lading. BIMCO observes that under English law the clause might be read as applying to bills of lading because it refers generically to “party,” and offers optional wording confining the cargo subclause to the carrier.


What This Means in Practice

For Drafting: Specify the events. The clause in MUR Shipping listed restrictions on monetary transfers and exchanges, which is why a sanctions-driven payment difficulty was capable of falling within it at all.


Decide whether reasonable endeavors should extend to accepting non-contractual performance. If so, say it in clear words and say in what circumstances, because the court held both are required.


Distinguish alternatives from options. A contract may permit payment in either of two currencies, or discharge at alternative ports, but the drafting has to make clear whether that is an obligation performable in alternative ways or a discretion one party holds. A true business option may not have to be exercised merely to avoid a force majeure event.


Set the notice requirement deliberately. A fixed period gives certainty and risks being missed. “Without delay” avoids arguments about when the event occurred and gives less certainty. If you use excluded days, say whose calendar.


Say what the consequence is. Suspension, a right to terminate after a period, an obligation to consult on rescheduling, or a combination.


Check what your force majeure clause does not cover, and whether a separate clause covers it. Sanctions are the clearest example.


For Operations: Diarize the notice obligation the moment anyone becomes aware of a potential event.


Document the endeavors. The party invoking the clause carries the burden of showing the event could not have been avoided by reasonable steps, and that is an evidential question later.


Pursue the contractual route first. Seeking a license or an alternative that enables performance as agreed is what the proviso requires. Arranging something different is not.


Take advice before refusing an offer from the counterparty. MUR was right on the law and still spent six years establishing it.


Where the Insurance Sits

Force majeure and insurance respond to different triggers. A successful force majeure claim does not itself establish an insured loss, and invoking the clause does not engage a policy. The underlying event may independently be an insured peril, a fire or a storm being the obvious examples, but that is a separate question answered by the policy rather than by the charter party.


Loss of hire is damage-based with extensions that vary. Standard loss of hire cover responds to specified damage-related events rather than to a commercial suspension of performance. Some programs extend to physical blockage, war risk interruption or forms of detention. Whether lost earnings are recoverable depends on the insured peril, the wording and the exclusions, not on whether a force majeure clause can be invoked.


The dispute itself is FD&D territory. Freight, demurrage and defense cover responds to the legal costs of pursuing or defending claims of this kind, including charter party disputes involving no physical loss, subject to the club’s rules and the merits.


The Bottom Line

English law gives you no force majeure relief except what your contract provides. The clause has to cover the event, the event has to cause the failure to perform, and the failure has to be one that reasonable endeavors could not have avoided. That last requirement will generally be read in even without an express proviso, subject to the wording and context.


MUR Shipping settled what reasonable endeavors does not mean. It does not require the affected party to accept something other than what the contract promised, absent clear words saying so. The reasoning was causation, freedom of contract, the principle that valuable rights are not given up by implication, and commercial certainty.


The drafting lesson runs the other way from the holding. If you want flexibility when things go wrong, build it in deliberately, and be clear whether what you are creating is an obligation performable in alternative ways or an option somebody can decline to exercise. Then check the notice provision, because a clause that bars the claim for late notice will decide the matter before anyone reaches the merits.